Cashmere Data Center Phase 2 Update

Here's an update on this full Electrical & Mechanical Expansion project. We're taking what was a shell of a building and ramping it up to 2MW usable data space power. With the addition of redundant air delivery system, full ducting to cold aisles, enclosure of hot aisles, powered exhausting of all hot aisle spaces, and addition of large commercial chiller system we can ensure 99.99% uptime during all weather conditions.